METPROM to Design a Mining & Processing Plant with Capacity Expansion up to 10 mtpa of Ore at PAVLIK-2 Gold Ore Deposit (Magadan Region)
METPROM will design a mining and processing plant at Pavlik gold ore deposit in order to expand the capacity of the gold recovery facility from 5 up to 10 mtpa of ore (second stage). The production program provides for a gravity separation-flotation-cyanidation process flow with 3 main stages: · Crushing · Benefication; · Metallurgical treatment (hydro- and pyrometallurgy).
Under the contract with PAVLIK Gold Ore Company, METPROM will be the general designer and also perform the design management functions. The facilities include: · Open pit mine facilities. Open pit site; · Open pit mine facilities. Dumping ground; · Site: · Tailings facility