JSC Polyus Krasnoyarsk
Customer
Blagodatnoye deposit Gold Recovery Plant No. 5
Facility
2021 — 2023
Timeframe
Construction of 8.3 mtpa Gold Recovery Plant No.5 (Mill-5)
Project
  • Civil and structural works at the facilities:
  • Main ore transportation conveyor
  • Crusher house
  • Crushed ore storage with feeders
  • Truck weighing station
  • Open pit mine infrastructure
Composition of work
  • Excavation - 5,000 m3
  • Construction of monolithic reinforced concrete structures - 13,000 m3
  • Installation of steel structures - 2,500 tons
  • Installation of equipment - 870 tons
  • Installation of pipelines - 7,600 m
  • Installation of wall panels and profiled flooring - 9,500 m2
  • Cable laying - 55 km
  • Supply of auxiliary equipment and materials
Scope of work
Over USD 600 m
Investment volume