Technical revamping of Continuous Pickling Line No. 4
Project
General design
A range of works for the shutdown period: dismantling of Process Line No.1 complete equipment and foundations, construction of foundations and erection of CPL No.4 complete equipment.
A range of works: dismantling of Process Line No.2 complete equipment and foundations, construction of railway tracks, ramps and the storage area for pickled hot-rolled coils.
Composition of work
Over RUB 4 bn
Investment volume
→
Swipe
←
Average daily production: 6,030 t
Design capacity: 2 mtpa of products
Performances
Dismantling of equipment and steel structures - 3,500 tons
Dismantling of reinforced concrete structures - 9,500 m3
Installation of process equipment - 3,000 tons
Installation of steel structures - 2,000 tons
Installation of reinforced concrete structures - 6,000 m3