Metallurgical Plant named after B.I. Kolesnikov 
 Sulfuric Acid Neutralization. Power generation facilities and utility networks 
  Civil and structural works, commissioning 
 - Excavation — 175,000 m3
- Foundations and foundation framework — 10,000 m3
- Installation of steel structures — 5,800 tons
- Installation of equipment — 250 tons
- Installation of pipelines and valves — 1,300 tons