NLMK
Customer
Novolipetsk Steel Plant
Facility
2009
Timeframe
Design of Blast Furnace No.7 “Rossiyanka” complex
Project
METPROM specialists developed a feasibility study (design) for the revamping of NLMK's blast furnace shop with the construction of Blast Furnace No. 7 and developed detail design documentation for the main process unit, casthouse and GCP; METPROM also provided designer supervision services.
Composition of work
RUB 43.6 bn
Investment volume
Swipe
Blast furnace volume: 4300 m3

Design capacity: over 3.4 mtpa of hot metal

Recovery co-gen plant capacity: 150 MW

The Blast Furnace No.7 "Rossiyanka" project employs most advanced green technologies – highly efficient dedusting systems, closed-loop water recirculation system, maximized recycling of BF off-gas to generate in-house electric power at the co-gen plant constructed as part of the BF complex.
Performances
  • METPROM was in charge of:
  • Blast furnace cooling system;
  • Industrial wiring of the BF, casthouse, stove unit, cyclone
  • Casthouses No.1 and No.2;
  • Construction of a runner system with covers;
  • Ducts of the casthouse dedusting system;
  • Main and auxiliary casthouse equipment
Facility composition