NLMK
Customer
Novolipetsk Steel Plant
Facility
2018 — 2020
Timeframe
Technical revamping of BOF Shop No.2
Project
Engineering surveys and studies
Design documentation
Detail design documentation
Composition of work
RUB 1 bn
Investment volume
→
Swipe
←
The revamped infrastructure (auxiliary) facilities enable NLMK to boost its capacity up to 14.2 mtpa of steel.
Perfomances
Revamping of the shop with a new maintenance area for crane No.18
Technical revamping of the maintenance area for the middle charging crane, bay V-G, gridlines 19-20;
Technical revamping of the shop with installation of a 120 t tong crane in bay L-M;
Expansion of the slab yard building, gridlines 62-68 of bay N-S;
Technical revamping of the ladle area;
Installation of a non-driven scrap car in charge preparation area No. 2;
Charge preparation area. Technical revamping of the proportioning area;