Mechel PAO
Customer
Chelyabinsk Metallurgical Plant
Facility
2019 — 2020
Timeframe
1st category overhaul of Blast Furnace No. 4, including the stove unit, casthouse, bottom house, skip pit, stockhouse.
Project
  • Dismantling of equipment - 901 tons
  • Dismantling of steel structures - 769 tons
  • Dismantling of cast iron plates and steel doors – 1,285 t
  • Dismantling of brickwork and lining - 1,967 m3
  • Dismantling of pipelines - 16,188 m
  • Installation of brickwork and lining - 2,101 m3
  • Installation of equipment - 943 tons
  • Installation of steel structures - 903 tons
  • Installation of pipelines - 16,667 m
  • Installation of cast iron plates and steel parts - 1,364 t
Scope of work
Over RUB 3 bn
Investment volume
Swipe
The shell and refractory inner lining of the blast furnace were completely reconstructed during the revamping project. New equipment was installed, including a fully upgraded updated blast furnace cooling system.
Composition of work