Welding of the BOF vessel (pre-assembly) — 95 r.m.
Welding of the waste heat boiler (pre-assembly) — 2,716 r.m.
Pipe insulation — 1,432 m3
Dismantling of pipe insulation — 1,442 m3
Dismantling of steel structures — 1,042 tons
Installation of steel structures — 1,370 t
Dismantling of equipment — 1,270 tons
Installation of equipment — 1,127 tons
Dismantling of pipelines — 2,289 m
Installation of pipelines — 4,239 m
Cable laying — 129,637 m
Dismantling of concrete and reinforced concrete structures — 333 m3
Installation of concrete and reinforced concrete structures — 331 m3
Объем строительно-монтажных работ
Over RUB 3 bn
Investment volume
→
Swipe
←
The works for the project included: replacement of BOF No. 1, gas cleaning system downstream the off-gas duct, waste heat boiler, ID fan, process control system and instrumentation, works on infrastructure facilities of the BOF Shop building