CJSC LMZ
Customer
Lysva Metallurgical Plant
Facility
2014 — 2016
Timeframe
Construction of a cold rolling shop (Construction of a flat rolling complex) 110 thou tpa color coating line (to apply "Print" coating)
Project
  • Design documentation
  • Detail design documentation
  • Supply of auxiliary equipment
  • Civil and structural works, commissioning
Composition of work
Over RUB 1.5 bn
Investment volume
Swipe
Design capacity: 820 thou tpa, including:

  • hot-dip galvanized flats - 400 thou tpa
  • prepainted flats - 220 thou tpa
Perfomances
  • Installation of process equipment - 3,000 tons
  • Installation of steel structures - 20,000 tons
  • Construction of reinforced concrete structures - 15,500 m3
  • Excavation - 12,300 m3
  • Small bore pipelines (<100 mm) – 400 m
  • Large bore pipelines (>100 mm) – 600 m
  • Electrical equipment - 50 pcs
  • Electrical cables - 45,000 m
  • Instrumentation - 80 pcs
  • Installation of hydraulic system - 180 t
Scope of work