Construction of hot rolling, cold rolling and thermomechanical treatment shops
Project
Installation of process equipment - 3,200 tons
Installation of steel structures - 3,000 t
Small bore pipelines (<100 mm) - 10 m
Large bore pipelines (>100 mm) – 20 m
Electrical equipment - 5 pcs
Electrical cables - 7500 m
Installation of hydraulic system - 70 t
Scope of work
→
Swipe
←
A range of works for erection and commissioning of process equipment supplied by SMS Meer, installation of process pipelines, hydraulic pipelines, cabling and electrical equipment.