ArcelorMittal
Customer
ArcelorMittal Temirtau
Facility
2013
Timeframe
Turnkey design and construction of a dedusting and gas cleaning system for Rotary Lime Kiln No. 3.
Project
Swipe
  • Capacity 300 thou m3/h.
  • Total gas flow 142 000 m3/hour
  • Dust concentration at the system inlet 6,800 mg/Nm3
  • Dust concentration at the system outlet 45 mg/Nm3
Performances
METPROM delivered the project on a turnkey basis. The company’s specialists developed design and detail design documentation, supplied equipment, carried out the entire range of civil and structural works, rendered commissioning and startup services.
Composition of work
  • Installation of process equipment - 1,000 tons
  • Installation of steel structures - 300 tons
  • Construction of reinforced concrete structures - 1,000 m3